YWCA Building Updates http://www.ywcayakima.org/ YWCA Bringing it Home Building Updates en-us info@ywcayakima.org info@ywcayakima.org September 2011 http://www.ywcayakima.org/blog_detail.html?blogid=57 We Did It Yakima!
Nearly three years ago, the YWCA moved into the new Emergency Family Shelter, with families moving into the new space just before Christmas. The new shelter provides a safe and ...
2011-11-10 http://www.ywcayakima.org/blog_detail.html?blogid=57
July 2011 http://www.ywcayakima.org/blog_detail.html?blogid=50 To celebrate the near completion of our Bringing it Home project, the YWCA hosted a reception on June 22 nd at the new facility; donors, business owners and neighborhood representatives were invited ... 2011-08-09 http://www.ywcayakima.org/blog_detail.html?blogid=50 April 2011 http://www.ywcayakima.org/blog_detail.html?blogid=48 The month of April was busy; the transitional housing units are nearly complete, with walls and ceilings painted, flooring and kitchen cabinets installed, and the tile work in the bathrooms done. Most... 2011-08-01 http://www.ywcayakima.org/blog_detail.html?blogid=48 May 2011 http://www.ywcayakima.org/blog_detail.html?blogid=49 The YWCA Yakima "Bringing it Home" project is nearing completion! All the finish work, plumbing, electrical, flooring and cabinetry has been completed in the housing units. The exterior courtyard ... 2011-08-01 http://www.ywcayakima.org/blog_detail.html?blogid=49 January 2011 http://www.ywcayakima.org/blog_detail.html?blogid=41


...
2011-04-12 http://www.ywcayakima.org/blog_detail.html?blogid=41
February 2011 http://www.ywcayakima.org/blog_detail.html?blogid=42


...
2011-04-12 http://www.ywcayakima.org/blog_detail.html?blogid=42
October 2010 http://www.ywcayakima.org/blog_detail.html?blogid=26



The renovations on the Bringing It Home project are moving forward on schedule; October was an exciting month, with many accomplishments achieved. The interior framing has been completed, sheet ...
2010-11-04 http://www.ywcayakima.org/blog_detail.html?blogid=26
September 2010 http://www.ywcayakima.org/blog_detail.html?blogid=25



September saw significant progress at the Bringing It Home construction site. The roofing work is nearly 90% complete, the electrical crews are on-site, interior framing work continues, and ...
2010-10-18 http://www.ywcayakima.org/blog_detail.html?blogid=25
July Construction Update http://www.ywcayakima.org/blog_detail.html?blogid=22 BRINGING IT HOME
“a place to encourage hope, enrich lives and empower dreams”
August, 2010
Construction work on Phase II of the Bringing It Home project was officially launched May ...
2010-09-03 http://www.ywcayakima.org/blog_detail.html?blogid=22
August 2010 http://www.ywcayakima.org/blog_detail.html?blogid=24



The month of August was very busy at the Bringing It Home construction site. We are pleased to report that the majority of the demolition work was completed at the end of July, and all the ...
2010-09-03 http://www.ywcayakima.org/blog_detail.html?blogid=24